City Council Approves Main Street Striping Contract
Information from City of Medford

At its September 2 meeting, the Medford City Council approved a $368,352.25 contract with Specialized Pavement Marking, LLC, to remove and reinstall striping on Main Street. The work will cover approximately 3,000 linear feet between Oakdale Avenue and 8th Street.
In May, the Council voted 5-2 to ratify its April 15 decision to rescind a previous January vote to revert Main Street to three lanes and instead move forward with a new configuration known as “Option 2A.”
This configuration includes two travel lanes, angled on-street parking on the left curb, parallel parking on the right curb, and a one-way bike lane.
The option is estimated to cost approximately $1.25 million total, including sign and signal work and repayment of previously awarded Oregon Department of Transportation grant funding.
Work is well underway, with an estimated completion date of October 31, 2026.